The PMOffice™ timesheet can also be configured
to capture Earned Value metrics. As resources post time against project
task assignments, they can also provide percent complete information.
Too often, EV calculations are based on the percentage
of time spent (Level of Effort or LOE). In reality a resource can spend
90% of the scheduled effort accomplishing only 10% of the work. This means
that the cost to perform 10% of the work is 90% of the budget. Industry
standard EV calculations rely on the 10% completed to calculate the actual
earned budget. The Earned Value Band displays BCWS, CV, BAC, ACWP, EAC,
VAC, BCWS, SV,CPI, SPI and Critical Ratio.

Earned Value Metrics
The information entered by project performers
is immediately aggregated and displayed in a myriad of other PMOffice
views, allowing the project managers and executives to obtain real-time
collaborative information and make sound decisions.
|
 |